September 28, 2018
Finishing concrete curb on south side of Sandy Blvd.

Traffic Control

  • Both traffic lanes were open this week.
  • There will be lane closures and traffic delays the week of Oct. 1 during paving and grinding work. Consider using alternate routes such as Interstate 84, NE Marine Drive and NE Halsey Blvd.

Recent Work

  • The curb was completed on the south side of Sandy Blvd.
  • Four catch basin inlets were installed
  • The contractor graded and compacted the aggregate base rock on the south side of the road.

Next Week

  • The contractor will pave the base lift of asphalt pavement.
  • The contractor will build forms for the south sidewalk at the wall location by the trailer park.
  • The contractor plans to do base paving on the south side of Sandy Blvd. on Monday.
  • Pavement grinding is planned on Tuesday.
  • Weather permitting, the top pavement layer should be installed after the pedestrian island is installed in early October.

Project webpage: www.multco.us/sandy