• Location: NE Corbett Hill Road, at the curve above NE Reed Road (location map)
  • Schedule:  First phase: October 15-18, 2018. Second phase: November 13-16, 2018.
  • Funding Source:  County Roadway Funds

Project Description

This project replaced a stormwater pipe that runs under Corbett Hill Road. The pipe had deteriorated, causing the road to crack and sink.  The repairs were completed in two phases, separated by several weeks.  Both traffic lanes were open between the work phases.

Traffic Impacts

Corbett Hill Road remained open, but there were lane closures during working hours.