Project Information

Location: Southeast shoulder of SW Military Road at intersection with SW Military Court (location map)

Schedule: Culvert installation completed, final paving scheduled for Friday, August 17, 2018 from 8 am to 5 pm.

Estimated Total Cost: $60,000

Funding Source: County General Roadway Funds

Project Description

We removed an open-bottomed concrete culvert that has eroded over time, causing the road surface to settle. It was replaced with a 36-inch concrete pipe that drains into an armored ditch. The ditch is northeast of SW Military Court.

The hole is filled with temporary surfacing and is scheduled to be paved with asphalt on Friday, August 17, 2018 from 8 am to 5 pm.

Traffic Impacts

One lane of Military Road will be closed during construction. Flaggers will be present to direct traffic.

No detour will be required. Those who want an alternate route may use SW Riverwood Road.

Military Court will be closed during the work. Access will be provided across the work area when work in not in progress.