Rendering of a bridge with two arches on either side of a central span with no arch.
Example of a Tied Arch Long Span
Rendering of a bridge with a single arch on the east side of the river.
Example of Tied Arch Long Span with West Girder
Rendering of a bridge. The two outer spans each have two small towers, with many cables running down from the top in a fan-like pattern to connect to the edges of the span.
Example of a Cable Stayed Long Span
Rendering of a bridge. The east span has two small towers, with many cables running down from the top in a fan-like pattern to connect to the edges of the span.
Example of Cable Stayed Long Span with West Girder
Rendering of a bridge span passing over Waterfront Park with two pairs of pillars supporting it in the park.
Example image of West Girder in Waterfront Park
Two renderings. The first is labeled Vertical Lift, and shows an entire bridge span being lifted between two pairs of towers while remaining level. The second is labeled Bascule, and shows a bridge span with no towers opening and lifting from the center l
Example Movable Span Types

The Replacement Long Span Bridge was recommended as the preferred bridge alternative to move forward into design after it is approved by Multnomah County and the Federal Highway Administration. The alternative will replace the existing Burnside Bridge with a new movable bridge in the same location and length as the existing bridge with support structure above the roadway surface resulting in fewer columns below. This means there are longer spans, or distances, between columns. It was recommended because it is the most seismically resilient with the lowest cost and fewest impacts to natural resources.

Multnomah County and the Earthquake Ready Burnside Bridge project team appreciate the hard work of the Community Task Force and public input on the recommendation of the Replacement Long Span as the project’s Preferred Alternative, the lowest cost of the alternatives studied. However, given the current competition for funding of large infrastructure projects, the elected leaders and management staff at Multnomah County who oversee the EQRB project have asked the project team to consider ways to bring the project cost down. At the same time, the County is working to identify and secure more funds. The aim is to achieve the right balance between the project design and the project cost, ensuring that the project can get built. The County has access to about $300 million for the project from its local vehicle registration fee. The cost range for the Preferred Alternative in the Draft EIS exceeded $800 million.

Finding cost-savings will require changes to the recommended Preferred Alternative that do not reduce the bridge’s ability to withstand a major earthquake. Before making any decisions, we are going to carefully analyze the implications of these potential cost-reduction measures:

  • Reducing the overall width of the bridge by eliminating a vehicular lane and providing bicycle/pedestrian facilities of at least 14-feet on each side with a crash worthy barrier. This change could lower project cost by approximately $140-$165 million.
  • Selecting a ‘girder’ structure type for the west approach that would place two rows of support columns in Waterfront Park. This would have fewer than the four rows of columns in the park that support the existing bridge, but more than some of the span types initially considered for the west approach. The girder structure type was endorsed by the Portland Historic Landmarks and Design Commissions because it does not conflict with the lower building heights in the historic districts and provides more open space above and below the bridge on the west approach. This change is expected to lower project cost by about $5-$10 million.
  • Adding a row of support columns on the east approach in or adjacent to the Burnside Skatepark for the Tied Arch. We are exploring ways to make this change with minimal impact to the Skatepark. Cost savings are estimated at $15-$20 million.
  • Funding the least cost option for connections to the Skidmore MAX station and Eastbank Esplanade. This analysis will ensure ADA access is provided to these important facilities below the bridge. The County is seeking opportunities to partner with other agencies to fund facilities and amenities beyond the lowest cost option. 
  • Limiting the budget for aesthetic enhancements by focusing on the main structural form of the new bridge to define its look and feel.
  • Others. We’ll keep looking for additional opportunities to keep costs down.

The evaluation of proposed cost reductions, development of detailed cost estimates and continued funding work will occur from spring to winter 2021. County leadership will use this information to establish a cost cap (or ‘not to exceed’) number for the project to ensure the project stays at an affordable price. The project team will document these findings along with an updated recommended Preferred Alternative in a Supplemental Draft Environmental Impact Statement in early 2022 for public and agency review and comment. 

To learn more about why these changes are being studied now, review the Frequently Asked Questions

Other Alternatives Considered

While the Replacement Long Span was identified as the Preferred Alternative, the Draft Environmental Impact Statement studied four alternatives and a no-build (or do nothing) alternative. The other alternatives considered and evaluated include:

1. Enhanced Seismic Retrofit - This alternative would upgrade the existing bridge. While this option allows for the preservation of portions of the historic Burnside Bridge, it requires replacement of some elements, extensive retrofitting of others, and retains many columns in unstable soil near the river. The cost of the retrofit is greater than building a new Long Span bridge.  

2. Replacement Short Span - This would be a new movable bridge at about the same surface height and location as the current bridge. It would have fewer columns than the current bridge, but more than the Replacement Long Span. This option is more expensive, has greater natural resource impacts and presents more seismic risk than the Replacement Long Span because it requires more columns in unstable soil near the river.

3. Replacement Northeast Couch Extension - This alternative would be a new movable bridge featuring a new westbound extension of Couch Street over NE 3rd and NE 2nd Avenues that would connect to the bridge over the river. While this option would smooth out the current S-curve on Couch Street, it requires many more columns in unstable soil near the river, increasing seismic risks and making it the most expensive alternative studied. It would also have the greatest impacts to natural resources, businesses, and bicycle access on the east side.


Traffic Management During Construction

The project team and Community Task Force considered two ways to manage traffic during bridge construction, which is expected to last four to five years starting in 2025. 

Bridge Closure With Detour

The recommended Preferred Alternative for managing traffic during construction is to fully close the bridge and detour all vehicles, bikes and pedestrians to neighboring bridges. This alternative was recommended because it reduces construction time and cost and reduces impacts to natural resources and parks.

Rendering of a new bridge under construction with a smaller temporary bridge alongside it.
Temporary Movable Bridge

The other alternative considered was to build a temporary movable bridge to maintain some level of traffic over the Willamette River at Burnside Street. The temporary bridge was not recommended because it would add $90 million to the project cost, add another 1.5 to 2 years to the overall construction duration and have additional impacts to natural resources.  

Watch a video to learn more about the recommended Preferred Alternative for managing traffic during construction.

All these alternatives were studied as part of the Environmental Review Phase. Findings from the analysis were documented as part of the Draft Environmental Impact Statement.